The three-road maintenance actions include 1) shoulder repair on Forest Road 236, 2) intersection clearing and reshaping on Forest Road 258 and Forest Road 236 and 3) widening and shoulder stabilization along Forest Road 419.
Location
Three locations, north of Highway 2, about 15 miles west of Ashland, WI. Two locations are along Forest Road 236, Brinks Road. One location is along Forest Road 419, north of Finger Lake.
Project timeline
1
Scoping Start
02/18/2026
2
Decision
03/2026 (Estimated)
3
Implementation
05/2026 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (23), 36 Cfr 220.6(E)(23) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance |
| Township Road Actions for Timber Haul and Safety | Decision Signed Date: 03/11/2026 |
| Forests | Chequamegon / Nicolet National Forest |
| Districts | Washburn Ranger District |
| Legal Land Description | Not Applicable |