Rebuilding stairway down to the lake
Location
South East side of Star Island
Project timeline
1
Scoping Start
11/01/2024
2
Decision
09/2025 (Estimated)
3
Implementation
09/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| East Beach Lot 10A- Staircase Rebuild | Decision Signed Date: 09/03/2025 |
| Forests | Chippewa National Forest |
| Districts | Blackduck Ranger District |
| Legal Land Description | T146N, R31W, Section 36 |