Proposed expansion is 50 feet x 90 feet for a total of 0.13 acres to expand parking for wildland fire vehicles and snowplowing.
Location
Behind the Rapid River Ranger District Office near Warehouse H.
Project timeline
1
Scoping Start
06/13/2025
2
Decision
08/2025 (Estimated)
3
Implementation
09/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (21), 36 Cfr 220.6(E)(21) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| Rapid River Office Compound Parking Lot Expansion | Decision Signed Date: 08/25/2025 |
| Forests | Hiawatha National Forest |
| Districts | Rapid River Ranger District |
| Legal Land Description | Not Applicable |