Decision Memo Completed

Southern Indiana Power Transmission Line Relocation

Hoosier National Forest Perry, Indiana Hoosier National Forest All Units

Proposal to relocate the existing 3-phase overhead power line closer to Old State Road 37.

Location

Along Old State Road 37 near Leopold, IN

Project timeline

1
Scoping Start
09/29/2025
2
Decision
03/2026 (Estimated)
3
Implementation
03/2026 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Southern Indiana Power Transmission Line RelocationDecision Signed Date: 03/11/2026
ForestsHoosier National Forest
DistrictsTell City Ranger District
Legal Land DescriptionT. 5 S., R. 2 W., Sections 11 and 22
Special use management