Proposal to relocate the existing 3-phase overhead power line closer to Old State Road 37.
Location
Along Old State Road 37 near Leopold, IN
Project timeline
1
Scoping Start
09/29/2025
2
Decision
03/2026 (Estimated)
3
Implementation
03/2026 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Southern Indiana Power Transmission Line Relocation | Decision Signed Date: 03/11/2026 |
| Forests | Hoosier National Forest |
| Districts | Tell City Ranger District |
| Legal Land Description | T. 5 S., R. 2 W., Sections 11 and 22 |