Project timeline
1
Scoping Start
02/28/2022
2
Comment Period
07/03/2024
3
Objection Period Start
11/27/2025
4
Decision
01/2026 (Estimated)
5
Implementation
01/2026 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Species Habitat Improvements |
| Kirtland's Warbler Habitat Management Plan | Decision Signed Date: 01/20/2026 |
| Forests | Huron-Manistee National Forest |
| Districts | Mio Ranger District; Huron Shores Ranger District |
| Legal Land Description | 26N05E, 26N04E, 26N03E, 25N01E, 24N07E, 23N07E, 25N03E, 25N07E, 25N02E, 26N02W, 26N01E, 25N01W, 25N04E, 24N06E, and 23N06E |