Chub Lake Re-Plow- plowing in underground powerlines along existing. Deep Lake Road-plowing in underground powerlines along existing road ROW.
Location
T60N R10W Section 17; T60N R10W Section 21; T60N R10W Section 28.T60N R10W Section 26; T60N R10W Section 23.
Project timeline
1
Scoping Start
09/01/2025
2
Decision
10/2025 (Estimated)
3
Implementation
11/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Cooperative Light & Power- TOF409005 LAU409005 KAW409006 Amendment 11 | Decision Signed Date: 10/22/2025 |
| Forests | Superior National Forest |
| Districts | Kawishiwi Ranger District |
| Legal Land Description | Not Applicable |