Replace the Sawyer River 2 bridge with a similar bridge type. A project-specific forest plan amendment is needed to exempt the bridge from the standard on page 2-31 of the forest plan.
Location
Sawyer River 2 bridge along Sawyer River Road, off route 302 in Bartlett, Carroll County, New Hampshire.
Project timeline
1
Scoping Start
01/03/2023
2
Comment Period
08/04/2023
3
Objection Period Start
11/07/2024
4
Decision
01/2025 (Estimated)
5
Implementation
05/2025 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Plan Amendment; Road Improvements/Construction |
| Sawyer River 2 Bridge Replacement and Project-Specific Forest Plan Amendment | Decision Signed Date: 01/08/2025 |
| Forests | White Mountain National Forest |
| Districts | Saco Ranger District |
| Legal Land Description | Not Applicable |