Project focus would be to convey the dam, which will result in a similar land use and alleviate the maintenance burden from the Forest Service. This would be a direct sale to the permittee of the special use permit.
Location
Campton Dam, Town of Campton, Grafton County, New Hampshire (NH) Mad River, NH Route 49, Pond Road
Project timeline
1
Scoping Start
03/29/2024
2
Decision
04/2027 (Estimated)
3
Implementation
04/2027 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (7), 36 Cfr 220.6(D)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Boundary Adjustments; Hydropower; Land Purchases; Facility Maintenance; Land Exchanges |
| Forests | White Mountain National Forest |
| Districts | Pemigewasset Ranger District |
| Legal Land Description | Not Applicable |